RURAL INDUSTRIES PRIVATE BAG 11 INNOVATION CENTRE
PHONE 393. 392, 448 & 449
KANYE BOTSWANA
SMALL SCALE DESALINATION FOR REMOTE AREAS OF
BOTSWANA
By R. YATES and T. WOTO
MAY 1988
FINAL REPORT OF A RESEARCH PROJECT FUNDED BY THE
INTERNATIONAL DEVELOPMENT RESEARCH CENTRE, OTTAWA, CANADA 1984 -
1987
CONTENTS
Acknowledgements PREFACE Executive
Summary
PART ONE
- INTRODUCTORY
1.1
INTRODUCTION 1.2
PROJECT TEAM AND DEVELOPMENT 1.3
THE FUTURE OF THE DESALINATION PROGRAMME
PART TWO
- THE WATER SITUATION IN THE DESERT
2.1
THE NEED FOR WATER 2.2
AFFECTED GROUPS - THE KALAHARI REMOTE AREA DWELLERS 2.3
THE RADS : AN ETHNIC PERSPECTIVE 2.5
THE RADP AND SMALL-SCALE DESALINATION 2.6
THE DROUGHT SITUATION IN THE DESERT AND RELATED RELIEF PROGRAMMES
PART
THREE - THE TECHNOLOGY
3.1
OPTIONS TO PROVIDE WATER 3.2
WOODBURNING STILLS 3.3
SOLAR DESALINATION 3.4
MEXICAN STILLS 3.5
BRICK STILLS 3.6
OTHER TYPES OF SOLAR STILL 3.7
PERFORMANCE OF THE STILLS 3.8
OPERATION AND MAINTENANCE OF STILLS 3.9
INSTALLATION OF STILLS 3.10
COSTS AND ECONOMIC ANALYSIS OF SOLAR STILLS
PART
FOUR - THE SETTLEMENTS
4.1
CHOICE AND NATURE OF SETTLEMENTS 4.2
THE RESEARCH SETTLEMENTS 4.2.1
Case Study 1 : Khawa 4.2.2
Case Study 2 : Lokgware 4.2.3
Case Study 3 : Zutshwa
PART
FIVE - TRAINING AND TECHNOLOGY ACCEPTANCE IN THE FIELD
5.1
TRAINING AND TECHNOLOGY ACCEPTANCE AMONG THE RADS 5.2
FIELD EXPERIENCES WITH WOOD-BURNING STILLS 5.3
FIELD EXPERIENCES WITH SOLAR
STILLS 5.3.1
KHAWA 5.3.2
ZUTSWHA 5.3.3
LOKGWARE : a case of technology rejected 5.4
FINAL EVALUATION SURVEYS : KHAWA AND ZUTSHWA
PART SIX
- TRAINING AND ACCEPTANCE WITHIN THE ADMINISTRATION
6.1
TRAINING AND ACCEPTANCE AT LOCAL AND CENTRAL GOVERNMENT LEVEL 6.2
EVALUATION SURVEY
REFERENCES APPENDIX
1 - A MAINTENANCE MANUAL FOR SOLAR STILLS PRESENTED BY R.
YATES APPENDIX
2 - LAYOUT AND CONSTRUCTION MANUAL FOR THE MK II MEXICAN
STILLS APPENDIX
3 - SALT PRODUCTION AT ZUTSHWA APPENDIX
4 - RESOLUTIONS AT A DESALINATION SEMINAR HELD AT THE RURAL INDUSTRIES
INNOVATION CENTRE IN KANYE FROM 10TH - 13TH AUGUST 1987 APPENDIX
5 - SUMMARY OF PROJECT FINDINGS
Acknowledgements
The authors would like to offer thanks to all those who have helped
with this project. First of all to IDRC for supporting the project and
for taking the trouble to visit and see how things are in the field. To
Ron Alward who came as a consultant from Brace Research Institute and
continued to give support and advice. To MR J.D. Nyatanga for his tireless
support in the field, and to all the other staff at Kgalagadi District
Council who have spent time helping us. To those in Central Government,
particularly MR C. Lindblom of Ministry of Local Government and Lands for
their tolerance and time. To all the management and staff of RIIC who have
given help and advice without seeming to interfere. Especially to the
other members of the desalination team - Judge Tlhage (field officer),
Mooka Moetse (extension officer), Tefo Marcho (technician), Karabo Modise
(builder) and Piet Cooper (driver) who each spent about 1800 hours driving
or being driven around the desert, and whose efforts in temperatures from
44° C to -9° C in sun, hail, dust and rain, night and day, have carried
the project to completion. Finally thanks to the people of Khawa,
Lokgware and Zutshwa who were always honest, hospitable and helpful to
us.
PREFACE
This is the final report of a three year project to evaluate and then
to introduce a new technology for water treatment in certain areas of
Botswana. Solar desalination was already well developed and established
elsewhere, so the task was to adapt it to the local conditions and to
generate enough confidence for it to be accepted.
Many lessons were learnt in the course of the project not only about
desalination but also about how to get a technology accepted and how much
time and effort it takes to adapt an old technology to a new situation.
However appropriate a technology may seem, there will always be problems
which occur in real life which may influence its acceptance.
The information contained in this report is sufficient to make informed
Decisions about future desalination work in Botswana. The account of how
the project was run and what sort of problems occurred will also be
relevant to the implementation of other projects.
Executive Summary
One hundred and thirty desalination units made up of two types of solar
still, two of woodburning still and one reverse osmosis unit were tested
in remote settlements in the Kgalagadi District in Botswana. The only
alternative sources of drinking water at these settlements was that
delivered by council trucks.
The objective of the project was to see if desalination in any form
would be suitable for use in the remote area settlements in Botswana.
In two of the three test sites, the solar still technology was well
accepted, in the third it was not properly used and was finally removed.
Reasons for the failure include lack of commitment by the villagers and
the absence of a salt water supply to the stillsite. An attempt was made
at this site to introduce stills for individual households instead of as a
communal installation, but this system was even less satisfactory and is
not recommended.
Extensive training was given to the end users and to those in local and
central government whose support was needed. These training programmes
were essential to the final acceptance of the technology.
Throughout the project detailed surveys were carried out to assess the
impact of, and attitudes to the technology. By the end of the project
those settlements where desalination was accepted had benefited from other
council services which could only be introduced once water was
available.
It was concluded that solar desalination is an appropriate technology
for some remote areas of Botswana, and the money saved by not having to
truck in water soon justifies the investment. For successful operation the
stills should be set up as a communal installation with a full time
operator to look after them. Failure to keep the stills correctly filled
will lead to their rapid deterioration.
The technology has been accepted as a viable means of supplying
drinking water and already a further site with 176 stills is being
constructed. Two more sites have also been planned, all using funds from
the drought relief programme.
A summary of the findings of the project and a list of resolutions
passed by government and council staff at the end-of-project seminar, are
given in Appendices 4 and 5 at the end of this report.
Copyright 1997 © International Development Research Centre,
Ottawa, Canada reference@idrc.ca | Updated: 10
November 1998
- Table of
Contents < Previous Chapter - Top of Chapter
- Next
Chapter >
Resources | Research Programs | The Institution |
CRDI en français
|